Red Dirt

 

Where is the project?

Near Hennessey, Oklahoma, in Kingfisher and Logan Counties

 

What transmission line does the project connect with?

Interconnecting with the OG&E Mathewson to Woodring 345kV transmission line

 

What is the size of the project?

300 MW

 

What turbines are being used?

Accionia AW125-3.15 MW

 

How many turbines are being used?

95

 

Landowners and Acreage Involved:

The project area encompasses approximately 60,000 acres.

 

When did the project begin operating?

December 2017

 

Who purchased the power?

Grand River Dam Authority and T-Mobile

 

Who developed the project?

Red Dirt Wind Project, LLC, a wholly-owned subsidiary of Tradewind Energy, Inc.

 

Who owns the project?

Enel Green Power North America, Inc.

 